What your well-test vendor needs before mobilizing.
Most mobilization delays are missing facts, not missing trucks. Send a complete package once.
The point of the checklist
Vendors price and staff from a handful of facts. If those facts arrive as a thread of texts the night before, you get extras, the wrong iron, or a delay you will blame on the testing company.
Use this list whether you hire us or not. If you want us to turn it into an RFP and a shortlist, request a program review.
Send these items
- Well identity, surface location, and basin / field
- Well type and status (drilling, cased, completed, producing, injection)
- Objective: DFIT, DST, flowback, production / AOF, other
- Expected rates, pressures, temperatures, and fluids — even if they are ranges
- H2S: yes / no / unknown, and any measured values
- Timeline: need-by date, rig-on / frac-on constraints, daylight vs 24-hour
- Access, lease limits, flare / conservation constraints, water disposal path
- Who is the decision-maker on extras and stop-work
What good looks like
A two-page envelope plus a wellbore schematic beats a 40-page well file with no objective. Vendors can ask for directional surveys and metallurgy once they know the job.
See also the critical sour Alberta checklist if H2S is in play, and vendor shortlist and bid comparison if you are going to market.
Welltest Advisory provides independent program design, vendor matching, coordination, and data-package support. Licensed service companies perform field work, operate equipment, and hold the relevant tickets. AER-aware language on this site is planning guidance, not legal, regulatory, or engineering stamp advice.
Request a program review
Company, name, and phone required. You get a program outline within 1 business day. Alberta / Western Canada focus.